IBM could lose $836M data center contract in Texas

July 20, 2010
The company is in danger of losing a $863 million data center consolidation contract with the state if it can’t show some improvement in the next 30 days.

According to reporting by Nick Wakeman in WashingtonTechnology, IBM Corp. has been warned by the state of Texas that the company is in danger of losing a $863 million data center consolidation contract if it can’t show some improvement in the next 30 days.

According to the report, the state of Texas sent IBM a detailed letter July 16, listing 15 areas where the state says the company has fallen short. The biggest issue is that IBM has not completed the consolidation of the states data centers from 27 to two. A seven-year contract was awarded in 2006 and the consolidation was to be completed by December 2009. To date, less than 12 percent has been consolidated, according to the state.

“IBM promised an investment in people, processes and technology to bring the benefits of data center consolidation to the state of Texas," said Karen Robinson, executive director of the Texas Department of Information Resources. “We have had continual problems with basic service delivery and IBM has failed to deliver on their promises.”

The state's Department of Information Resources issued the warning, known as a “notice to cure,” to pressure IBM to improve. The move “follows months of unsuccessful attempts to find a collaborative solution with IBM,” the state said.

In a defensive statement, IBM said that it "has fulfilled its obligations under the contract and last week's action by DIR was unnecessary and unjustified. IBM has worked in cooperation and good faith with DIR to provide benefits and improvements to all citizens of Texas. IBM very much regrets the State's action and will aggressively protect its interests going forward."

According to the state, IBM and Texas negotiated a framework for improving work on the contract. The framework, called Agreements in Principle, was developed at the end of 2009, but by June 25 the state told IBM that the framework had failed.

In addition to the data center consolidation issue, IBM is accused of failing to perform backup and data recovery services, failure to deliver a disaster recovery plan, and not providing sufficient staffing. These and other issues put IBM in material breach of its contract with Texas, the state said in its notice to IBM.

SOURCE: WashingtonTechnology

Sponsored Recommendations

imVision® - Industry's Leading Automated Infrastructure Management (AIM) Solution

May 29, 2024
It's hard to manage what you can't see. Read more about how you can get visiability into your connected environment.

Adapt to higher fiber counts

May 29, 2024
Learn more on how new innovations help Data Centers adapt to higher fiber counts.

Going the Distance with Copper

May 29, 2024
CommScopes newest SYSTIMAX 2.0 copper solution is ready to run the distanceand then some.